L Taraval Improvement Project Reaches Key Milestone

L Taraval Improvement Project Reaches Key Milestone
By Jay Lu

Newly planted trees and shrubs on Taraval Street

While the past 18 months have been full of challenges and anxiety because of the pandemic, today we have good news to share. With community support and collaboration from our city partners, the SFMTA has successfully completed the first of two segments of the L Taraval Improvement Project. Construction of Segment A started in September 2019 and was completed in July 2021 on schedule and within budget.

This project was made possible in part by Proposition K Sales Tax dollars provided by the San Francisco County Transportation Authority. Our work on this first phase improved transit and infrastructure between Sunset Boulevard and SF Zoo, with close collaboration between the SFMTA, the San Francisco Public Utilities Commission (PUC), and San Francisco Public Works. Upgrades to this vital corridor that help the community thrive include: 

  • Rail track and overhead line replacement
  • Water and sewer line replacement
  • Surface repaving
  • Curb ramp upgrades
  • Concrete boarding islands and pedestrian bulbs
  • Traffic signals
  • New trees and landscaping

These improvements have made pedestrian crossing safer, increased accessibility and improved transit reliability for our customers while rehabilitating water & sewer infrastructure and enhancing landscaping to make Taraval Street more enjoyable for everyone.

We would like to thank Supervisor Mar, Sunset neighbors, local businesses and People of Parkside, Sunset (POPS) for their partnership in shaping and completing this project. We are especially grateful to the residents who live along the Lower Great Highway where the traffic and parking patterns had to change due to the lane closures for staging of construction materials and equipment.

The project couldn’t be a success without the close partnership between community stakeholders, sister city agencies, the contractor and SFMTA staff.

By partnering with PUC, we were able to identify potential utility conflicts early on. This led to our decision to split the project into Segment A and Segment B, which provide both PG&E and PUC the time needed to relocate underground utilities.

In collaboration with our contractor, NTK Construction, a comprehensive communications plan was implemented to provide clear, transparent information to local businesses and residents on staging areas, the construction approach and sequencing, things to expect, service interruptions and service support planning. To support local businesses and residents, special accommodations were made to minimize construction impacts.

To ensure successful project delivery, the project team reflected on the lessons learned from previous projects as important ways of gathering and sharing project knowledge among internal partners. Special acknowledgements to Construction Management team, Street Division, Communications and Outreach, Transit Planners and Maintenance of Way.

While celebrating the completion of Segment A, we are now gearing up for Segment B, which will make the same improvements from Sunset Boulevard to West Portal. Construction on this next phase is anticipated to start in early 2022 and last through the end of 2024.

Once completed, the nearly five-mile long corridor from West Portal to the Zoo will boast new transit priority traffic signals, bulbouts to make pedestrian crossing safer, new trees, high visibility cross-walks, safety boarding islands and increased accessibility. All of these changes will make Taraval more inviting for everyone that lives or travels there.

To follow the progress of this project as we move into the next phase, you can visit our webpage and sign up for updates.

Check out the photos below on construction work and achievements obtained in Segment A:



Published July 09, 2021 at 07:38PM
https://ift.tt/3wuM0BE

Comments

Popular posts from this blog

News from the WHO: The ceasefire in Gaza brings hope, but immense challenges lie ahead to restore the health system

Published on January 19, 2025 View on website

Have Feedback on the COVID-19 Muni Temporary Service Plan?

Have Feedback on the COVID-19 Muni Temporary Service Plan? By Shalon Rogers In March 2020, due to unprecedented constraints on resources brought on by the COVID-19 pandemic, the SFMTA had to make significant transit service reductions. As of January 2021, the agency has been able to restore service to a level where 91% of San Franciscans are within a quarter mile of a transit stop. This is reflected in the SFMTA’s current  COVID-19 Temporary Service Plan .   ' COVID-19 Temporary Service Plan Map The SFMTA is committed to ensuring that our programs and services are  compliant with Title VI of the Civil Rights Act of 1964  and therefore do not have a discriminatory impact based on race, color or national origin. As part of this work, we conducted a Title VI service equity analysis to evaluate the current COVID-19 Temporary Service Plan. The results of this analysis will be presented to the ...

Slow Streets are Full Steam Ahead

Slow Streets are Full Steam Ahead By Last week, the San Francisco Board of Supervisors ruled against four California Environmental Quality Act (CEQA) appeals that have been delaying Slow Streets, temporary emergency transit-only lanes, bike lanes and emergency street closures. Within 12 hours of the Board’s decision, SFMTA crews were back out in full force to implement these critical initiatives that help keep San Francisco moving during the pandemic.  The Board of Supervisors ruled unanimously that these temporary projects are deemed critical to the city’s emergency response efforts, preventing a further delay.  Implementation of new Slow Streets was put on hold while we waited for the appeals hearings, giving crews the opportunity to focus on filling in the signage gaps and repairing existing ...